INTRODUCTION
In my blogs I have been talking about the management of major projects. Though there is no specific criteria, but it is a generally accepted that a Major Project can be identified as a project with a minimum estimated total installed cost (TIC) of US$ 250 million and accompanied by a high level of complexity. A major project is a large-scale investment project and generally attracts a lot of public interest due to substantial impact on communities and environment. There are a variety of major projects and each project requires a distinct management approach and execution strategy requiring specialized technical skills, execution strategies and the adoption of strategic management philosophy. For example a project to construct a highway may require a different set of skills and execution strategies as compared to a large airport. Similarly the development of a housing complex may require a totally different skills and execution strategies as compared to an offshore oil drilling project.
It is observed that Oil & Gas, Energy, Process and
Power projects form a distinct group requiring a common platform of project
management techniques. This blog focuses on the management of this group of projects.
With the increase in technological growth and globalization
of industry, the scale and complexity of projects continue to increase. The
owners have started to realize that aggregating the processes, power,
technology and infrastructure generally leads to significant improvements in
project profitability. Only a few project managers hold the skills and
processes required to plan and deliver these projects. In the following
blogs, we will discuss the required skills, processes and procedures to
successfully deliver these major projects in an increasingly challenging
project delivery environment.
1.
What is EPC
EPC stands for Engineering,
Procurement and Construction. It is a
common form of contracting arrangement for the execution of Oil & Gas, Chemical and
Process industry. Under an EPC contract, the contractor takes complete
responsibility of engineering
the facility, installation, procuring the necessary equipment and materials;
installing and constructing, either through its own labor or by subcontracting
a part of the work.
E
E stands for engineering
only. Such contracts are awarded in the initial phases of the project to carry
out the basic design or FEED work. FEED stands for Front-End Engineering and
Design. For major projects, it is becoming a
common practice to split the project into two phases; in the first phase the
contractor sets the design parameters that define the work scope, prepare WBS, estimates, and break the work down into work packages to a level
sufficient for the award of a detailed EPC contract. The second phase consists
of the EPC or EPCM phase.
EP
When the execution scope is restricted to engineering and procurement only;
this is referred to as an EP contract. This is often done in situations
where the Owner has a preference for doing the construction through
its own resources or intends to award the construction work to a third party.
EPCM
When scope is
restricted to engineering, procurement and construction management only,
this is referred to as an EPCM contract.
2 . EPC AGREEMENTS
The EPC (or EP or
EPCM) agreements are of four major types:
a) LSTK CONTRACTS
LSTK stands for Lump
Sum Turn Key. It combines the Lump Sum (LS) part that refers to the payment of fixed fee under the EPC
contract. The second part TK stands
for Turn Key. TK specifies that the
scope of work includes the commissioning and start-up of the facility to
operational status.
b) LUMP-SUM CONTRACTS
Under Lump Sum
Contracts, the EPC contractor’s responsibility is limited to satisfying the
agreement terms (generally till the Mechanical Completion) for a fixed fee.
Some agreements cover the pre-commissioning activities as well. The owner takes
over the charge of project and completes the rest of the work including
commissioning, trial runs and plant operations.
c)
COST PLUS CONTRACTS
Under Cost Plus
Contracts, the EPC contractor is provided a specified percentage
profit over and above the actual cost of Engineering, Procurement and
Construction work. These contracts are quite popular with the Oil & Gas and
Petrochemical projects. Under these agreements, the owner has a good presence
in the project team with most of the decisions being taken jointly.
3. COST PLUS PROJECT TEAM
Under
the Cost-Plus contracts, project team consists of the Owner, the EPC Contractor
and third parties engaged on specific jobs. On account of the complex responsibility, decision
making and approval process, the formation of the project team under such agreements needs
a great deal of effort. It is therefore necessary to develop a detailed
responsibility matrix to define the responsibility and approval process of each
team member. A
detailed discussion on this subject will be done under RASCI blog.
4. ALLIANCE AGREEMENTS
Alliance agreement is a model of
co-operative work model that had become very popular in the EPC industry during
1990’s. Excessive cost over-runs and
project delays started a re-thinking in the industry leading to the alliance
agreements. The alliance contracting concept evolved as a response to two
perceived failings in the traditional model of EPC business. The first was the
excessively adversarial nature of the EPC contracts, driven by the traditional
LSTK agreements with liquidated damages. The second was the barrier to
outstanding project performance that was the need of the day.
No comments:
Post a Comment